Swimming pools and aquacentres
| |
Quimperlé aquacentre (29)
Creation of the gas-fired boiler room with radiators and heating floor.
• Pool Hall air treatment unit.
• Water treatment by disinfecting with ozone.
Works budget: €1,341,372 excl. VAT
Prime contractor: Communauté de communes de Quimperlé (District Council)
Architect: Jean-Yves PHILIPPE
Design office: ETHIS - Lorient
Work certificate: Click here
|
|

|
| |
Pléneuf Val André thalassotherapy centre (22)
Creation of a shield water production and distribution system on terminal units:
• 1 x 468 kW reversible air/water heat pump for the residences.
• 1 x 570 kW air/water heat pump
for the thalassotherapy centre.
Contract amount: €1,672,762 excl. VAT
Prime contractor: HMC
Architect: Philippe ROBERT |
|

|
| |
Saint Quentin urban leisure base (02)
Construction of an entertainment and sports type facility including a swimming pool, skating rink and bowling alley.
Works budget:
Water treatment/Heating/Ventilation: €4,100,000 excl. VAT
Architect: Chabannes
Design office: Katene
Delivery: Current 2009 |
| |
Lorient swimming pool
This swimming pool complex includes a 25m pool, a small activities pool, a 260m² entertainment pool with a counter-current river, a play lagoon, a toboggan and a diving pit.
Technical particularities:
The swimming pool heating is performed by a municipal wood-fired boiler and the swimming pool water is treated with ozone.
Delivery: 2006
Works budget:
Plumbing/Heating/Water treatment:
€1,700,000 excl. VAT
Architect: Jean-Yves PHILIPPE
Design office: ETHIS - Lorient |
|

|
| |
Versailles swimming pool
The swimming pool complex consists of covered Olympic pool, a 15m by 10m learner pool, a 300m² entertainment basin equipped with a hydromassage bench and various games.
A games lagoon and external paddling pool, both also animated by water features.
A health and fitness area complementing the aquatic activities.
Technical particularities:
Solar panels on the roof (210 m²)
Heat recovery for the sanitary hot water and for preheating the pools.
Delivery: 2006
Works budget:
Plumbing/Heating/Water treatment:
€2,032,578 excl. VAT
Architect: Jacques ROUGERIE
Design office: ETHIS - Lorient |
|

|
|
|